CONSTRUCTION SCHEDULE 4/8 TO 4/15
Posted on: April 7, 2022 - 10:12am
Updated schedule from Albanese for the week of 4/11 to 4/15.
Friday, 4/8
Crew 1, Install 8" connection at Palmetto
Crew 2, Install hydrant on Norris St
Monday, 4/11
Tie-In Palmetto (12")
Tuesday, 4/12
Tie-In Lakeview at Christine
Wednesday, 4/13
Cut/Cap 12" main at Parham/Sherbrooke and Tyngsboro/Stewart
Begin Liner install on Tyngsboro Rd
Thursday, 4/14
Remove hydrants along Lakeview/Tyngsboro
Continue lining
Friday, 4/15
Remove hydrants
Continue lining