Current Construction Projects

Spring/Summer 2022:  
The below infrastructure projects will improve water quality, increase water production at the Tyngsboro Well Field, improve water flow and pressure for the residents of Tyngsboro and provide redundancy of the water system.  Dracut Water Supply District thanks you for your cooperation and patience during your water system improvement projects.

16" Water Transmission Main:  Installation of the new 16" water transmission main by Albanese D&S is complete.  Final paving is scheduled at the end of July.  This is to allow the work done in April 2022 to settle for a minimum of 3 months as required by the specs. 

State Forest Water Storage Tank:  Work on the State Forest Tank by Preload started in July of 2021.  The old tank was taken offline and demolished and the new foundation and walls were poured before worked stopped for the winter.  Work resumed in May and the walls are scheduled to be raised 5/25/22.  The 64 ft tank is scheduled to be online in August of this summer.   

Water Treatment Plant:  The groundbreaking of the new water treatment plant to remove iron and manganese took place on 5/19/22.  The plant is scheduled to be completed in June of 2023.

groundbreaking  
                                                                                                                                                    
groundbreaking
                                                             

Spring/Summer 2021: Work will begin on the below main upgrade on Monday May 10, 2021.  The awarding contractor Albanese D&S will be starting on Tyngsboro Rd at Stewart St and working towards the Dracut/Tyngsboro line. 

                                                                                                                        main upgrade

Water Treatment Plant: Capital Improvement Plans -  The below link contains important information regarding some upcoming Capital Improvement Plans the District is hoping to accomplish in the coming years.  We are committed to providing safe,affordable and high quality drinking water to our customers while looking to the future infrastucture of the District.   

Click here to read about our Capital Improvement Plans

Summer/Fall 2018: The Dracut Water Supply District is upgrading water meters and has contracted East National Water, LLC for installation services.  Technicians from East National Water, LLC will be contacting residents with meters 10 years or older to schedule an appointment.  The installation service is free of charge and is mandatory.  Meter installers will be wearing company uniforms, using vehicles with East National logo and will be carrying a company issued photo id. We encourage you to always ask to see ID before allowing anyone in your home.  
 
 
Construction to install a new 16” water main from the District’s wellfield at Frost Road through Norris Road and Lawrence Road to Lakeview Avenue will begin Monday June 4, 2018 and will continue through November 30th.  The purpose of this project is to improve hydraulic loss, increase water flow, provide redundancy of the water system and minimize several pump stations.  This is a tremendous upgrade to the water system and future water demands.  
 

Summer/Fall 2017 - Under sized mains have recently been upgraded on Gilmore St, Harlem St, Sparks St, Park Terrace, Parkvale Terrace, Park Ave, Vermont Ave, Beacon St and Lakeview Terrace. Work will be finalized in the Spring 2018. 

  

construction

The District is continuing to redevelop and replace 2 of our wells at the Tyngsboro Well Field location. These upgrades will improve water quality.  We anticipate the first of the new wells to be online in the Summer 2018

 

 

construction

Summer/Fall 2018   Aqualine Utility has recently completed replacing aging infrastructure with a new water main from the State Forest Storage Tank on Tyngsboro Rd to the Varnum Ave Pump Station.  

 

Follow us on facebook for additional information and photos.